South West Region Public Lighting Project Update

Initial Surveying

Initial Surveying across the entire region is 100% complete.

Direct Feed Surveying

Direct Feed Surveying across the entire region is currently 74% complete.

Design Submissions

Design submissions have commenced in all 5No. Local Authorities.  40,114designs have been accepted, representing 67% of the designs required in the region.

Retrofit of Public Lights

Contractor ActivityCommence% Complete
Cork Co Co Municipal Districts
Bandon – Kinsale12 April 202367.2%
Carrigaline10 July 202352.1%
Cobh09 October 202356.2%
Macroom29 April 202444.9%
Kanturk – Mallow06 November 202341.3%
East Cork23 October 202361%
Fermoy27 May 202456.8%
West Cork11 January 202430.6%
 % of Retrofitting complete in Cork County49.9%
 
Kerry Co Co Municipal Districts  
Castleisland-Corca Dhuibhne   34%
Kenmare  30 September 20240.6%
Killarney  TBC 
Listowel  12 August 202427.7%
Tralee  08 July 202438%
 % of Retrofitting complete in County Kerry29.2%
 
Waterford City & Co Co Municipal Districts  
Waterford City  TBC 
Comeragh  TBC 
Dungarvan – Lismore12 August 202429.5%
 % of Retrofitting complete in County Waterford7.6%
% of Retrofitting complete across the region28.6%