PLEEP-SW National Website Update; 14 December 2022
Table 1: Contract Appointments
Contract Milestones | Design Build Works Contract | Consultancy Services Contract |
Contract Date | 28 January 2022 | 4 January 2022 |
Starting Date (as per NEC) | 31 January 2022 | – |
Planned Contract Completion | 2nd Sept 2024 | 2nd Sept 2024 |
Defects Period | 2nd Sept 2024 – 2nd Sept 2026 | 2nd Sept 2024 – 2nd Sept 2026 |
Progress Update: (9 Dec 22)
- The contractor has progressed with surveying and condition rating of the Public Lighting assets as noted in Table 2.
- There are 27,433 (approx.) Public Lights surveyed and condition rated to-date (9 December 22) in Cork County which equates to 80% (approx.) The Next County to commence surveying is Kerry in January 2023.
- Submission of Design packs for review and acceptance commenced 2 December 22.
Table 2: Contractor Progress
Contractor Activity | Commence | Complete |
Contractor Mobilisation / Set-up | 31 January – 24 April 2022 | – |
Contractor Activity | Commence | Complete |
Surveying | ||
Cork County Council Municipal Districts | ||
Bandon Kinsale | 25 April 2022 | 16 June 2022 |
Carrigaline | 24 May 2022 | 9 August 2022 |
Cobh | 10 August 2022 | 27 September 2022 |
Macroom | 26 September 2022 | 17 October 2022 |
Kanturk Mallow | 11 October 2022 | Ongoing |
West Cork | 7 November 2022 | Ongoing |
East Cork | 17 November 2022 | Ongoing |
Fermoy | Commence Shortly | – |
Contractor Activity | Commence | Complete |
Design Submissions | ||
Cork County Council Municipal Districts | ||
Bandon Kinsale | 2 December 2022 | – |