The contractor has progressed with surveying and condition rating of the Public Lighting assets and commenced retrofit as noted in Table 2.
There are 50,340 (approx.) Public Lights surveyed and condition rated to-date (20 Apr 23) in Cork, Waterford and Kerry which equates to 100% for Cork, 51% for Waterford and 49 % for Kerry (approx.)
There are 100 (approx.) Public Lights retrofitted to date in Cork. Retrofit commenced on 12 Apr 23.
Submission of Design packs for review and acceptance are ongoing.
Project Material Samples being received for review and acceptance.
Table 2: Contractor Progress
Contractor Activity
Commence
Complete
Contractor Mobilisation / Set-up
31 January 2022
24 April 2022
Contractor Activity
Commence
Complete
Surveying
Cork County Council Municipal Districts (All now complete)
Waterford City & County Council Municipal Districts